We were commissioned to design and deliver a comprehensive water and gas infrastructure upgrade at Bulkhaul’s facility – a project critical to supporting a new steam generator installation. Working within the client’s existing site boundary, our team managed both utilities simultaneously, minimising disruption and ensuring a compliant, future-proofed solution.
The project presented several technical challenges from the outset. There were no drawings available for the existing underground water pipework, requiring our engineers to make informed assumptions about pipe type and sizing. On the gas side, the existing U40 meter was undersized for the demands of the new steam generator, necessitating an upgrade to a new U100 meter – and the booster pump system had to be designed to minimise any downtime during the transition.
We planned the water supply works to make use of the existing connection within Bulkhaul’s boundary, avoiding the need for a new utility meter and reducing both programme time and cost. The installation was designed for safe isolation, reliable monitoring and protection against weather conditions before commissioning.

We used the existing on-site connection to simplify the installation and avoid unnecessary utility works.
Connected to the existing water supply adjacent to the gas meter house
Completed all works within Bulkhaul’s boundary
Avoided the need for a new meter from Northumbrian Water
Reduced project time and overall installation cost

The new arrangement was designed to give Bulkhaul clear monitoring and safe access for isolation.
Installed an additional water meter to monitor supply to the steam generator
Fitted an isolation valve within the existing gas meter house
Provided safe and accessible shut-off for maintenance and operation

To ensure reliability in service, the system was protected, tested and prepared for operation.
Carried out full pressure and flow testing before commissioning
Applied weatherproof pipe insulation throughout the installation
Installed trace heating along the pipe run to prevent freezing in winter
The gas works were centred around the installation of a new U100 meter, replacing the undersized U40, located between the switch room and the boundary wall. Our installation encompassed:

The gas installation was built around upgrading the existing meter arrangement to suit the new steam generator.
Installed a new U100 gas meter to replace the undersized existing U40
Positioned the new meter between the switch room and the boundary wall
Improved gas capacity to support the new steam generator reliably

The booster pump arrangement was designed to provide resilience while keeping the equipment protected on site.
Supplied and installed a dual booster pump for operational redundancy
Helped maintain steam generator operation during maintenance periods
Adapted a client-provided steel container unit to house the booster pump assembly
Created a secure and weatherproof enclosure for the new equipment

The remaining gas infrastructure works were completed to deliver a safe, tested and fully compliant installation.
Completed the full gas pipe installation
Carried out pressure testing and Gas Safe certification
Constructed a dedicated gas meter housing to protect the new U100 meter
Installed a gas safety solenoid valve interlocked with the site fire alarm system
Enabled automatic gas shut-off in the event of an emergency
The project was completed safely, on programme and in full compliance with the relevant standards.
Bulkhaul now has a reliable, future-ready water and gas infrastructure arrangement to support the long-term operation of its steam generator. The dual booster pump setup improves resilience, the fire alarm interlock enhances safety, and the insulated, trace-heated water supply supports dependable performance throughout the year. By managing both utility installations together, we delivered a joined-up solution with minimal disruption to site operations.
At EIT LTD, we are committed to delivering the best mechanical, plumbing and gas services available. With decades of experience, we combine technical expertise with exceptional customer service. Our team is fully qualified, insured and committed to maintaining safety standards, giving you peace of mind with every project.
We offer:
When we inspect a plant room or gas installation, we document findings clearly and prioritise actions by risk. That gives clients the information they need to make confident decisions - and keep sites safe and compliant.
Vince Peel - EIT Ltd Operations & Contracts Director
If you are responsible for plumbing or gas systems in a commercial building and need reliable support, our team can help. Whether you require installation, servicing, planned maintenance, or urgent fault response, we will provide clear advice and professional delivery.